This is your connection to Downtown. The East High streetscape project includes portions of Market Street, 9th Street, and East High Street.

This map shows the continuation of the East High Street Corridor from the Belmont Bridge Project. Click here to view the Belmont Bridge Project website.

News and Updates

On January 30, 2026, the City invited contractors to bid on the East High Street construction project. Work will span East Market Street (7th to 9th), 9th Street (E. Market to E. High), and East High Street (9th to Locust/10th). The project includes relocating water, sewer, and gas utilities; building an underground duct bank on 9th Street; and upgrading traffic signals and ITS at several intersections. Bids close March 31, with construction expected to start July 6. Updates on road closures and impacts will be posted online.

Community Events

 

For more information about upcoming meetings and to contact the project team, visit the Get Involved page.